Latest Notification

Time and work


                                                                          Time  and work

It is one of the easiest topic in quant section. This topic is can fetch you marks easily but you need to know the right concepts and types of questions to practice.
We need to understand relation among time, work done and number of employees working. Since efficiency of different person is different. We discussed all such problem under the heading of “time and work”.
Here we are explaining two method to solve time and work question one in basic method and other LCM method .so my point is that you follow both the method which one is easy for you .but I want to told about LCM method if your concept are clear properly then you follow LCM method otherwise you follow basic method it is also easy method. According to me you follow best to basic method.  

1.       Lets a person  do a piece of work in x days. Then person one day’s work=1/x
2.       Person one day’s work=1/x, then person can finish the work in x days.

3.       A can finish 1/x part of  work in a day and B can finish 1/y part of work in day.
If both  will be working together to finish the task then in a day they can finish

1/x+1/y=x+y/xy work in one day
part of the work so to finish the work it require
xy/x+y days.


Q1. If A can do a work in 8 day, B can do the same work in 12 days. How many days are required to finish the task if both are working together ?

Basic method

 

A’s 1 day’s work = 1/8
B’s 1 day’s work = 1/12
(A+B)’s 1 day’s work=1/8+1/12=20/8*12=5/24 part of work
So the whole task finished in 24/5 days. i.e. 4.8days

 

LCM method












Notes :- Time=total work/efficiency


A+B’s day=24/5=4.8 days

Q2.  If A can do a work in 4 day, B can do the same work in 5 days and C can do the same work in 10 days.  Find the time taken by A, B and C to do same work in together.

 Basic method


A’s 1 day’s work = 1/4
B’s 1 day’s work = 1/5

C’s 1 day’s work = 1/10

(A+B+C)’s 1 day’s work=1/4+1/5+1/10==11/20 part of work
So the whole task finished in 20/11 days. i.e. 1.8181days

LCM method













(A+B+C)’s days of work= 20/11=1.8181 days.

2. When A and B work in alternate days


Case 1:

 

Starting from A
Lets A can finish the in 8 days and B can finish the task in 10 days. How many days required to finish the task if both are working alternate days?

Solution :


A’s 1 day’s work = 1/8 part
A’s 1 day’s work = 1/10 part
Both are working alternately starting from A
Then in first two days they can finish 1/8+1/10
8+10/80=18/10
If they continue in such a manner together in 8 days they can finish 72/80 part of work
Remaining part-  8/80=1/10
Finished by A in 9th day so. To finish 1/10 part
A need
1/10*8/1=4/5days.
So, together they can finish the task in 8and 4/5days

In the above question calculate number of days required to finish the task by A and B if both are working alternately starting from B
Solution:
Work still remain same has to finished by B.

(If they start working alternately starting from B, then on 9th day it will be B’s turn)
B can finish 1/10part of the work in 1/10*10/1=1 days
So, together they can complete the task in 9th days.

LCM method

Case 1.

Starting from A
  Efficiency                                    day                       total work
         10                     A                     8
                                                           80
8                B                10     

(A+B)’s days of work= 80/18
If they continue in such a manner together in 8 days they can finish 72/80 part of work
Remaining part-  8/80=1/10
Finished by A in 9th day so. To finish 1/10 part
A need
1/10*8/1=4/5days.
So, together they can finish the task in 8and 4/5days

Same like B.


4. Concept of after and before leave the work  











No comments